Garda Uno Completes Bid Review for 16 Sewer Projects Worth Over 7 Billion Lire

With a grueling “no-stop” effort that kept officials from the Azienda Speciale Consorzio Garda Uno busy for two intense days, the work of the committee tasked with reviewing the bids submitted for the construction of the 16 lots scheduled, with a total value of over 7 billion lire, has concluded.

Selection and composition of the Committee

A sort of gift under the tree for the numerous companies that secured, through the discount offer, the various projects based on the “base contract amount.”

Eighty companies submitted their bids for the 16 available lots, each focused on one or more lots (generally on almost all lots), each corresponding to a municipality. Nine Brescia-based firms won 12 lots.

The Committee was composed of: arch. Franco Richetti (Garda Uno General Director) as president; ing. Giampietro Avanzi and geom. Pietro Pirlo as members; dr. Fabrizio Gatti as secretary.

Timelines and project delivery

The delivery of the works, subject to legal reservations and pending the contract, is scheduled by Christmas. The actual start of the construction sites is already set for the first days of January 1999.

Very tight dates and deadlines that all companies must adhere to, completing the work within the timeframes already specified in the tender notice.

The longest commitment in terms of work is for the first lot (sewers in Limone and Tremosine), with a scheduled 510 working days: “natural and consecutive days starting from the date of delivery of the delivery report,” recall Garda Uno officials.

The shortest is the 12th (sewers in Soiano), which is expected to be completed in 60 days. But let’s see the different assignments.

Details of lots and awardees

Lot 1 (sewers in Limone and Tremosine) base amount 3,500,000,000 lire, deadline 510 days: Quadrio S.P.A. from Morbegno (SO) with a 17.22% discount.

Lot 2 (sewers in Gardone Riviera) amount 246,000,000 lire, deadline 120 days: I.C.O. Italia S.r.l. from Tursi, discount 14.75%.

Lot 3 (sewers in Gargnano) amount 162,000,000 lire, deadline 140 days: Pavoni S.p.A. from Vobarno, discount 7.1%.

Lot 4 (sewers in Roè Volciano) amount 202,000,000 lire, deadline 120 days: Marzocchi Bruno e Figli S.n.c. from Calvisano, discount 10.22%.

Lot 5 (sewers in Salò) amount 320,000,000 lire, deadline 140 days for the first phase; 450,000,000 lire and 150 days for the second phase: C.B.C. from Bedizzole, discount 13.45%.

Lot 6 (sewers in Tignale) 154,000,000 lire, deadline 90 days: Perini S.n.c. from Tremosine, discount 8.5%.

Lot 7 (sewers in Toscolano Maderno) 243,000,000 lire, deadline 120 days: Vaglia Nicola S.n.c. from Condino (TN), discount 11.39%.

Lot 8 (sewers in Manerba) 330,983,909 lire, deadline 120 days: I.C.B. S.r.l. from Edolo, discount 11.76%.

Lot 9 (sewers in Moniga) 280,000,000 lire, deadline 120 days: Pelizzari S.r.l. from Collebeato, discount 14.63%.

Lot 10 (sewers in Puegnago) 162,000,000 lire, deadline 120 days: Gilioli S.n.c. from Lonato, discount 12.75%.

Lot 11 (sewers in San Felice) 166,000,000 lire, deadline 120 days: Edilnord S.p.A. from Molinetto di Mazzano, discount 17.4%.

Lot 12 (sewers in Soiano) 165,222,374 lire, deadline 60 days: Pavoni S.p.A. from Vobarno, discount 10.95%.

Lot 13 (sewers in Desenzano) amount 245,000,000 lire, deadline 120 days: Zeviani from Legnago, discount 13.88%.

Lot 14 (sewers in Lonato) 425,000,000 lire, deadline 180 days: CBC from Bedizzole, discount 16.23%.

Lot 15 (sewers in Padenghe) 162,000,000 lire, deadline 120 days: CBC from Bedizzole, discount 14.15%.

Lot 16 (sewers in Sirmione) 82,765,601 lire, deadline 90 days: BTT S.n.c. from Manerba, discount 8.55%. Both awarded and excluded firms will be directly notified over the next few days regarding the outcome of the “tender” itself.